RERA Registered or RERA Approved: Using the Right Terminology in Practice
By CA Vinay Thyagaraj and CA Deena Davis
Introduction
In Part 1, we examined why the RERA Act provides for project registration rather than general project approval. This distinction becomes particularly important when describing a project in advertisements, professional opinions, compliance reports and communications with prospective purchasers.
Can the words Registered and Approved be used interchangeably?
In ordinary conversation, a person may use “RERA Approved” to convey that a project has obtained RERA registration. Promoters, agents and professionals should avoid this usage in formal communications, opinions, advertisements, compliance reports and publications.
This expression may create an impression that the RERA Authority has independently sanctioned the project, certified its construction standards or quality, guaranteed its completion or endorsed its commercial merits. Registration does not, by itself, establish any such guarantee.
A Kerala Real Estate Regulatory Authority direction concerning the use of “RERA Approved” in advertisements clarified that the Authority grants registration rather than project approval and directed promoters to use the registration number in the prescribed manner. The relevant direction is contained in Kerala RERA Order No. K-RERA/T3/102/2020 dated 18 November 2020.
A published Telangana RERA order concerning the Diamond Sai Teja Township matter also addressed the use of “RERA Approved” in promotional material in circumstances where registration was absent.
Accordingly, use “RERA-registered” when referring to a project registered under the RERA Act. Use “approved” only for a particular plan, permission or proposal that has in fact been approved by the respective competent authority.
For RERA, the primary sources remain Sections 3, 4 and 5 of the Act, the applicable State rules and regulations, and relevant directions or orders of the concerned RERA Authority.
What terminology should promoters and professionals use?
| Situation | Recommended expression |
|---|---|
| Project has obtained registration under RERA | RERA-registered project |
| Referring to the statutory process | Registration granted under Section 5 of the RERA Act |
| Referring to the number allotted by the Authority | RERA registration number |
| Building plan sanctioned by the competent authority | Building plan approved by the competent authority |
| Layout sanctioned by the planning authority | Approved layout, or layout approved by the competent authority |
| Application submitted but registration not granted | Application for RERA registration submitted, if verified |
| Project exempt from registration | State the applicable exemption and its legal basis; do not imply that the project is registered. |
The terminology should accurately describe the status of the project or the particular approval being referred to. Submission of an application is not the same as the grant of registration, just as approval of a layout is not the same as registration of the real estate project under RERA.
What happens when project approvals and RERA registration do not match?
The following hypothetical scenarios illustrate why registration and approvals must be examined separately.
Scenario A: Registered, but approvals do not match
Project A, a hypothetical apartment project in Bengaluru, displays a valid RERA registration number and is marketed as “RERA Approved”.
On review, the commencement certificate covers only Towers 1 and 2, whereas the registration and the sales collateral cover Towers 1 to 3.
A lender’s Chartered Accountant should:
- Compare the sanctioned plan with the registered project scope.
- Ask the promoter to explain the inclusion of Tower 3.
- Restrict disbursement to the sanctioned area.
- Record that RERA registration does not cure the approval gap.
The discrepancy may raise issues under Section 14 concerning adherence to sanctioned plans and under Section 12 concerning the veracity of advertisements or prospectuses, depending on the facts.
Scenario B: Layout approved, but project unregistered
Project B, a hypothetical plotted development on the outskirts of Bengaluru, has obtained layout approval and land-conversion approval and is selling 40 plots. However, the land area exceeds 500 square metres and no Karnataka RERA registration has been obtained. Buyers’ advances are held in the promoter’s general account.
Approval does not displace the requirement of Section 3.
A Chartered Accountant advising a prospective investor should flag the potential penalty under Section 59, examine any applicable refund rights under Section 18, assess compliance with the separate-account requirements, and consider any contingent liability that should be reflected in the promoter’s accounts.
The central issue is that an approval granted by a planning authority does not, by itself, establish compliance with the registration and financial obligations under RERA.
How should RERA registration be described in advertisements and marketing?
Many real estate advertisements, particularly those aired on FM radio and other mass-media platforms, describe projects as “RERA Approved”. Although this expression may be used to convey credibility and reassure prospective buyers, it is important to understand the correct legal terminology.
Promoters, advertising agencies, broadcasters and real estate agents should therefore exercise care while using these expressions. “RERA Registered” is the more accurate expression when referring to a project that has obtained registration under the Act.
Allottees and prospective buyers should verify the project’s registration details on the relevant State RERA website and independently examine the applicable approvals and other project documents, rather than relying solely on the terminology used in advertisements.
Conclusion
“RERA Approved” is a marketing phrase, not a legal status under the RERA Act. The Act provides for the registration of real estate projects and agents. Project registration brings timelines, funds and disclosures within the applicable regulatory framework, without itself endorsing the project’s title, design, quality or viability.
Planning, building and occupancy permissions remain separate matters for the competent authorities. Neither can those approvals substitute for RERA registration where it is required, nor can RERA registration substitute for those approvals.
For Chartered Accountants and other professionals, this means treating registration, statutory approvals and compliance with the separate-account requirements as three distinct questions, and testing each against primary records: the State RERA portal, sanctioned plans and certificates, and the project’s bank account and books.
Where the answer to any of these questions is incomplete, the consequences may affect buyers, lenders and promoters through refund claims, penalties, disclosure exposure or audit qualifications, depending on the circumstances.
Accurate terminology and documented verification form part of competent professional advice. As the RERA Act, State rules and case law continue to evolve, such verification should be repeated rather than assumed.
Adapted from “RERA Registered or RERA Approved” by CA Vinay Thyagaraj and CA Deena Davis, originally published in the KSCAA News Bulletin, October 2026.
All your questions answered

Ask for the project’s RERA registration number and verify its details on the relevant State RERA portal. Separately examine the sanctioned plans, applicable approvals and project documents. The advertising phrase alone does not establish registration or approval status.
Promoters should use RERA registered and display the registration number and other particulars in the manner required by the Act and applicable State directions. RERA approved can misleadingly suggest a broader endorsement by the Authority.
Yes. Layout approval and RERA registration are separate processes. If Section 3 requires registration and no exemption applies, layout approval does not permit the promoter to bypass that requirement.
Compare the registered project scope, sanctioned plans and relevant certificates. Ask the promoter to explain the discrepancy. RERA registration does not cure an approval gap; Sections 12 and 14 may be relevant depending on the facts.
No. An application submitted for registration is not registration granted under Section 5. A project should not be described as RERA registered merely because an application is pending.
The source article cites Kerala RERA Order K-RERA/T3/102/2020 dated 18 November 2020, which addressed the use of RERA approved in advertisements and directed use of the registration number in the prescribed manner. It also refers to a Telangana RERA order concerning Diamond Sai Teja Township. Consult the official orders for their precise scope.
Disclaimer:
The information contained in this article is provided for general informational purposes and does not constitute legal advice. Readers should not act or refrain from acting on the basis of any content included herein without seeking appropriate legal or professional advice on the specific facts and circumstances at issue.