Telangana RERA Invokes Force Majeure; Grants 4-Month Extension to Real Estate Projects

Author: Orders & Circulars

Introduction:

Those familiar with Section 6 of the RERA Act will know that it provides for the extension of project registration in the event of Force Majeure. Against this backdrop, and following a recent advisory from the Ministry of Housing and Urban Affairs (MoHUA), the Telangana Real Estate Regulatory Authority (TGRERA) has issued an order granting a four-month extension to eligible registered real estate projects. The order covers projects whose completion date, revised completion date or extended completion date falls on or after 28 February 2026, with the prevailing West Asia situation being treated as a “war” for invoking Force Majeure.

TGRERA's Order

Sub: TGRERA – Extension of registration of Real Estate projects affected by the prevailing West Asia situation, treating it as “war” for the purpose of Force Majeure under the provisions of the Real Estate (Regulation and Development) Act, 2016 for a period of four months after 28.02.2026 – Orders – Issued.

Ref: Advisory issued by the Government of India, Ministry of Housing and Urban Affairs (Housing Division) in No.O-17024/66/2018-HOUSING-UD/E-9042100 Dated: 31.07.2026.

The Government of India, Ministry of Housing & Urban Affairs (Housing Division), vide reference cited above, has advised all Real Estate Regulatory Authorities that, in exercise of the powers conferred under the provisions of the Real Estate (Regulation and Development) Act, 2016, they may issue suitable orders or directions for the grant of extension of registration and corresponding completion timelines of registered Real Estate Projects whose completion date, revised completion date, or extended completion date falls on or after 28 February 2026 for a period of four months, treating the West Asia situation as a “war” for the purpose of invocation of the Force Majeure clause.











    In view of the above orders, and in terms of Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 6 of the Telangana Real Estate (Regulation and Development) Rules, 2017, this Authority hereby issues the following orders:

    “The validity of registration and corresponding completion timelines of registered Real Estate Projects under TGRERA, whose completion date, revised completion date, or extended completion date falls on or after 28 February 2026, shall stand extended for a period of “four months.”

    Explanation: For the projects whose completion date, revised completion date or extended completion date falls between 28th Feb 2026 and 31st July 2026, the completion timelines shall stand extended up to 30th Nov 2026.

    It is further ordered that there is no requirement for the submission of separate individual applications or the payment of any fees for this extension.

    (By Order of the Hon’ble Authority)

    Secretary
    TGRERA

    Download the official copy of the TGRERA Order.

    All your questions answered (FAQs)

    RERA Consultants FAQs

    The Telangana Real Estate Regulatory Authority (TGRERA) has granted a four-month extension to the registration validity and corresponding completion timelines of eligible registered real estate projects. The extension has been granted considering the prevailing West Asia situation as a “war” for invoking the Force Majeure clause under RERA.

    Registered projects under TGRERA whose completion date, revised completion date, or extended completion date falls on or after 28 February 2026 are eligible for the four-month extension.

    For projects whose completion date, revised completion date, or extended completion date falls between 28 February 2026 and 31 July 2026, the completion timeline stands extended up to 30 November 2026.

    No. TGRERA has specifically stated that separate individual applications are not required for this extension. Eligible projects receive the extension in accordance with the Authority’s order.

    No. No fee is required for the extension granted under the TGRERA order dated 31 July 2026. The Authority has clarified that neither a separate application nor payment of fees is necessary.

    Disclaimer:

    The information contained in this article is provided for general informational purposes and does not constitute legal advice. Readers should not act or refrain from acting on the basis of any content included herein without seeking appropriate legal or professional advice on the specific facts and circumstances at issue.

    Related Articles

    We help you build your real estate brand, avoid penalties, and most importantly, go-to-market faster.

    Joint Development Agreement Under RERA: Key Legal and Compliance Considerations for Developers

    Joint Development Agreement Under RERA: Key Legal and Compliance Considerations for Developers

    Understand how a Joint Development Agreement under RERA impacts developers, promoter responsibilities, project registration, revenue sharing, and compliance obligations.
    Read more
    RERA Defect Liability Period: Promoters Must Know Before Project Handover

    RERA Defect Liability Period: Promoters Must Know Before Project Handover

    The Defect Liability Period under RERA under Section 14(3) creates continuing responsibilities for promoters even after possession is handed over.
    Read more
    The 3- Bank Account Rule under RERA: What Developers Need to Know

    The 3- Bank Account Rule under RERA: What Developers Need to Know

    Effective from 1 January 2026, every new RERA registration application in Tamil Nadu must comply with a structured 3-Bank Account framework designed to enhance fund...
    Read more